Parcel Model Update:  Revised Implementation Dates

 

Summary

The following is an update on the implementation schedule for the new Parcel Model.  There have been some adjustments to the schedule as a result of technical issues related to structuring and subsequent bidding involving both group 1 and group 2 employees.  

The goal is to implement the model in stages in order to ensure the most effective implementation.

 

Details

 

o        The YDC implementation began last week.  By October 25, 2004, all Expedited volumes will be added. On or before  January 4, 2005, all Xpresspost will be added.

o        At the West Parcel Delivery Hub, the implementation will begin with the running of the PAXIS sorter on October 17, 2004.  The new loop structure will be operational effective November 22, 2004.  Expedited volumes will be added by December 13, 2004, and Xpresspost will be added on or by January 4, 2005.

o        At the 1 Yonge Hub, the loops will be operational November 8, 2004.  Expedited will be added by November 24, 2005 and Xpresspost product will be added on or before January 4, 2005.

 

If you have questions, comments or suggestions about the Parcel Model, you can send them by email to gtapdmp@canadapost.ca - or if you work at one of the three parcel hubs, you can drop them in one of the boxes provided at those sites.  Responses to all questions will be published as quickly as possible. 

 