Home Up 07-12-12a 07-12-12b 07-11-30 07-11-29 07-11-29a 07-11-29b 07-11-22 07-11-09 07-10-22 07-09-20 07-09-18a 07-09-18b 07-08-29 07-08-22 07-08-08a 07-08-08b 07-07-05 07-06-29 07-06-22 07-06-22a 07-06-18 07-06-08 07-06-01 07-05-24 07-04-11 07-04-05 07-03-21a 07-03-21b 07-03-07 07-02-14a 07-02-14b 07-01-23 07-01-22 07-01-10a 07-01-10b

 

 

Home
Up

 

 

 

 

 

UNION/MANAGEMENT CONSULTATION

 

SCARBOROUGH DEPOT 11 PLAN “C” IMPLEMENTATION JUNE 18, 2007

 

May 16, 2007

 

Participants

 

Management                                                           Union

 

Derek Stever                                                           Tom Parkes

Randy Carroll                                                          Leary Charles

Jim Walling                                                              Ken Davidson

Mark Debreau                                                         Steve Chapman

Bo Mastinsek

 

A review of the restructure report show a net gain of 1 FT Letter Carrier and a reduction of 1 PT Letter Carrier. One CMB code M1J 2C8 was moved from PT walk 26 to PT walk 111, causing walk 111 to become FT.

 

The effective implementation date for this change will be June 18, 2008.

 

It was agreed that all part-time walks will be bid upon internally starting May 24, 2007 and ending on May 25, 2007. For first round bidding rights purposes it was agreed the restructure date of May 3, 2007 would be the cut-off date.

 

The senior part-time employee in the local is to be made full-time through the normal staffing process.

 

The start time for walk 111 was reviewed and it was agreed upon, subject to a possible review following implementation should any operational concerns necessitate a change.

 

The Union has agreed to waive the 15 day verification period.

 

Meeting adjourned.

 

cc All Participants

 